New York Litigation Update
December 13, 2000
In Windsor Metal Fabrications, Ltd. v. General Accident Insurance Company of
America, the court ruled that the one-year limitation period to sue a surety on
a public improvement construction bond, starts when a subcontractor has demanded
final payment from the general contractor and 90 days have passed since the
subcontractor ceased work on the project. The time period may not be extended or
overridden by provisions of the subcontract.
Eberhard Construction Company (Eberhard) contracted with the State of New
York to construct a healthcare center at the Greenhaven Correctional Facility.
Windsor Metal Fabrications, Ltd. (Windsor) subcontracted with Eberhard to
provide and erect structural steel. General Accident Insurance Company of
America (General Accident) provided the payment bond for the project. After
Windsor began its work, the state terminated its contract with Eberhard which
resulted in Windsor’s subcontract being terminated. Windsor won an arbitration
award against Eberhard; however, Eberhard was insolvent. Thus, Windsor sued
General Accident, which raised a statute-of-limitations defense. The trial court
granted General Accident’s summary judgment on this ground, which the
Appellate Division reversed. The Court of Appeals reinstated the trial court’s
ruling.
In F. Garofalo Electric Co., Inc. v. New York University, F. Garofalo
Electric Co., Inc. (Garofalo) contracted with New York University (NYU) to
install electrical systems on new buildings at NYU. Garofalo alleged the project
was delayed, and that NYU and its construction manager required and directed it
to perform extra work and to provide extra materials to the project not required
under the contract. Garofalo also alleged that NYU and its construction manager
orally agreed to pay for the additional work and additional materials, and
Garofalo performed the additional work and furnished the additional materials
based upon those oral representations. The Appellate Division reversed the trial
court’s allowance of these claims because satisfaction of the contract’s
notice requirements for extra work and delay damages was a condition precedent
to Garofalo’s recovery.
The Appellate Division held that the written contract (which provided that it
could be modified only in writing) could be modified orally only if the oral
modification was “fully executed” or there had been “partial performance
‘unequivocally referable’ to the oral modification.” There was nothing in
the record which could be viewed as “unequivocally referable to an intent to
modify the provisions in question.”