Illinois: Differing Site Conditions Under the Illinois’ Public Construction Contract Act
June 2, 2003
Gregory R. "Greg" Meeder- Chicago
The Illinois General Assembly enacted important new
legislation entitled the Public Construction Contract Act during its December
1999 veto session in an effort to promote competition among contractors and
save the taxpayers of Illinois significant construction dollars on public
construction contracts.
Illinois’ Public Construction Contract Act (P.C.C.A.)
requires that public construction contracts, between local units of government
and a contractor for improvements that exceed $75,000.00, contain a differing
site conditions clause. The differing site conditions clause establishes an
administrative procedure at the contract level for the resolution of disputes
when the physical condition of the improvement site: (a) is materially
different than that indicated in the contract; or (b) is unknown or unusual
and is not ordinarily encountered when performing the type of work covered by
the contract.
Upon discovery of a differing site condition, and before
further disturbing the physical condition of the site, the contractor must
notify the owner in writing if it is going to seek an adjustment to the
contract. The owner must determine if the physical condition would cause an
increase in the contractor’s costs or time. If the owner determines that there
will be an increase in costs or time, that determination will be put in
writing and become part of and modify the original contract. A contractor
cannot make a claim for additional costs or time because of a physical
condition unless he or she has given the owner the required advance
notification.
In carrying out construction work, a contractor sometimes
encounters circumstances at a site that had not been foreseen. Unanticipated
physical conditions may have an effect on the cost of completing the work
and/or the amount of time needed to complete the project. Examples include the
discovery of illegal underground dumps, old foundations, and unexpected soil
or rock conditions. The P.C.C.A. provides an administrative process at the
contract level for adjusting the contract price due to the discovery of the
unforeseen conditions. The P.C.C.A. further reduces the risks associated with
unforeseen conditions and reduces the cost of some projects because
contractors will not have to add contingencies to cover possible unexpected
circumstances. Taxpayers will not have to pay for contingencies that may never
happen. Also, the administrative process offered by the P.C.C.A. leads to
better relations among contracting parties and reduces the risk of litigation.
Past Historical Perspective and Law on Differing Site
Conditions
In the early days of contracting, public owners typically
provided no subsurface information to bidders. The entire risk of adverse
subsurface and latent conditions was, therefore, allocated entirely to the
bidder. Such a contract procurement philosophy forced contractors to cover
their risk by putting large contingency sums in their bids. Eventually
governmental bodies recognized that the inclusion of contingency sums in the
contract price caused them to pay windfalls to contractors when troublesome
conditions were not encountered. Drafters of government contracts sought a
means of inducing the contractors to eliminate contingency funds from their
bids.
Contractors, too, have a keen interest in this historical
problem. Particularly in underground construction or in the renovation of
existing buildings, bidders cannot predict unseen conditions without the
benefit of intrusive investigation. Typically, contractors only have a few
days or weeks to perform cost estimates and submit their bids. This does not
provide sufficient time for the contractor to perform its own investigation.
This problem also can be aggravated because projects are frequently within
public rights-of-way or on private property. Private property owners and
governmental bodies do not permit numerous prospective bidders to perform soil
borings, dig holes or tear out walls on their properties. Moreover the costs
of such investigations would be passed on to the project owners in the bid
prices. Such a practice would be expensive and duplicative, since the owners
pay for subsurface investigations during the design phase.
Under Illinois case law prior to the enactment of the
P.C.C.A., a contractor had no basis for a claim under the contract if it
encountered subsurface conditions or latent conditions that materially
differed from the conditions indicated in the contract documents. Before this
new legislation, a contractor could only assert a cause of action for
misrepresentation or a breach of the implied warranty of accuracy and
sufficiency of the plans and specifications or come up with some other
creative theory of liability.
Why Illinois Enacted the P.C.C.A.
Unfortunately, many public agencies and their consulting
engineers have failed to understand the history, purpose and benefits of the
differing site conditions clause. Public agencies and their consulting
engineers incorrectly believed that the clause produced too many claims and
unwarranted windfalls for the contractor. As a result, they refrained from
including the clause in their contracts. This practice fostered the evils that
the clause was designed to overcome: high contract prices across the board and
litigation over misrepresentation of subsurface conditions. In public agency
projects taxpayers foot the cost for this misunderstanding and bad practice.
Illinois’ P.C.C.A. was enacted in an effort to make
differing site conditions clauses part of the contracts between governmental
agencies and contractors carrying out large improvement projects. The P.C.C.A.
precludes windfalls, because the contractor only receives extra compensation
if it actually encounters troublesome conditions that materially differ from
the conditions indicated by the owner in the contract. This result is logical
and fair to all parties because, if the owner initially had accurately
indicated the correct conditions to the bidders the bid prices would have
been higher to reflect the more difficult working conditions.
The P.C.C.A. provides that it does not limit the rights
or remedies otherwise available to a contractor or the governmental entity
under any other law or statute. The term “contractor” does not apply to
architects, professional engineers and surveyors. Otherwise, the term refers
to an individual or entity that contracts with a governmental entity to
improve real property or perform or manage construction services. The term
“governmental entity” refers to a county, city, township, village, public
educational institution, or any political subdivision thereof. Lobbying
efforts on the part of the state, the County of Cook, and the Metropolitan
Water Reclamation District were successful in excluding these public bodies
from the P.C.C.A. However, IDOT, the Capital Development Board and the
Department of Natural Resources currently utilize a differing site conditions
clause in their contract documents. Home rule municipalities also may exempt
themselves from the statute. The term “improvement” includes but is not
limited to all or any part of any building, structure, erection, alteration,
demolition, excavation, clearing, grading, filling, landscaping, trees,
shrubbery, driveways and roadways on real property.
Gregory R. Meeder, a partner in the Construction & Design
Law Section at Holland & Knight LLC, authored the Public Construction Contract
Act and testified before the Senate and House Committees on behalf of the
Underground Contractors Association and the Illinois Construction Industry
Committee.
For more information, call Gregory Meeder, toll free, at
1-888-688-8500.