Recent Developments at GAO
March 1, 1999
Three recent decisions by the General Accounting Office may signal
significant changes in GAO's review of bid protests.
GAO Reverses Non-contract "Incidentals" Position
The first case, Pyxis Corporation, B-282469 (July 15, 1999), is a clear
reversal of GAO's previous position that federal agencies, when making purchases
under an existing contract, may also purchase non-contract
"incidentals" without further competition. In a 1997 decision, ViON
Corp., B-275063, 97-1 CPD ¶ 53, GAO authorized the purchase of "tag
along" items from a contractor as long as they were incidental to a primary
purchase under a Federal Supply Schedule (FSS) contract and were not a
significant part of the overall purchase price. Subsequent to ViON, however, the
Court of Federal Claims decided in ATA Defense Industries, Inc. v. United
States, 38 Fed. Cl. 489 (1997), that for purchases outside of FSS listed items,
an agency must use competitive procedures, because no exception to the
Competition in Contracting Act (CICA) "even arguably applies" to such
purchases.
In the Pyxis case, the Army had relied on ViON not only to purchase
"incidental" non-Schedule items, but also to receive different prices
and terms for items that were on the FSS. On July 15, 1999, GAO ruled that
"in light of the analysis of the court in ATA, ... there is no statutory
authority for the 'incidentals' test enunciated in ViON." GAO not only
overturned ViON with its Pyxis decision, it went out of its way to do so. Even
though the protest was untimely, GAO triggered its own bid protest rule that
gives GAO discretion to decide untimely issues that nonetheless are
"significant to the procurement system..." 4 C.F.R. § 21.2(c).
GAO Defines Protest Authority
In the second case, Makro Janitorial Services, Inc., B-282690 (August 18,
1999), GAO seems to be defining its protest authority in the face of a statutory
limitation on protests of task orders. The Federal Acquisition Streamlining Act
(FASA) prohibited protests in connection with the issuance of orders under a
task order contract or delivery order contract, except for protests that the
order increases the scope, period, or maximum value of the contract. FAR 16.505.
In Makro, the Army Corps of Engineers issued a task order for "Housekeeping
Services" under an indefinite-delivery/indefinite-quantity (IDIQ) contract
for "Real Property Inventory, Demand Maintenance Repairs and Surveys of
Medical Facilities." Makro protested the housekeeping task order as outside
the original scope of the contract.
GAO rejected evidence that the original contract provided for both
housekeeping and exterior grounds maintenance in finding the proposed
housekeeping services beyond the scope of the contract. GAO instead relied upon
background procurement documents and contract definitions and descriptions which
were heavily oriented toward functions that addressed the facilities' physical
plant, including repair, maintenance and minor construction. GAO concluded that
"[t]here is nothing in the original scope of work that even remotely
suggests that the contract contemplated the acquisition of housekeeping services
as defined by the modification."
While there is evidence in the record to support GAO's decision, the Corps'
position that facilities maintenance includes housekeeping did not seem to be
unreasonable. If this case signals GAO's intent to protect its remaining bid
protest authority over task order contracts, then one can reasonably expect
strict scrutiny of task orders when such "scope check" protests are
filed. Such strict scrutiny provides opportunities for protesters and a warning
to agencies.
Past Performance Evaluations
The third case of note was a garden variety past performance case. In AmClyde
Engineered Products Co., Inc., GAO found that the agency's evaluation of
AmClyde's proposal and past performance was reasonable and denied the protest.
Such denials are fairly common at GAO.
AmClyde alleged that the Navy had down graded its past performance "for
making claims." GAO found, in fact, that the Navy, had not cited AmClyde's
claims history during its past-performance discussions with AmClyde; and, even
if it had, it was not likely that would have affected the outcome of the
procurement.
GAO then dropped a footnote on the subject which makes for interesting
reading for agencies and protesters alike:
"While the claims apparently had no impact here, we agree with the
protester that, absent some evidence of abuse of the process, agencies should
not lower a firm's past performance evaluation based solely on its having filed
claims. Contract claims, like bid protests, constitute remedies established by
statute and regulation, and firms should not be prejudiced in competing for
other contracts because of their reasonable pursuit of such remedies in the
past."
GAO is not given to making gratuitous comments in its decisions. Federal
agencies will be well-advised to keep GAO's words in mind when evaluating the
past performance of its potential contractors.