Intent and Principles of Contract Construction Weigh in Favor of Closing Agent
September 17, 2002
The intent of the parties and basic principles of contract
construction set right a sale gone wrong. The Appellate Court of Illinois,
Second District, recently handed down a decision that serves as a reminder to
consider carefully the intent of the parties to a contract when crafting its
language. In Premier Title Company v. Duane Donahue, No. 2-00-1076 (Ill. App.
Ct. March 1, 2002),
http://www.state.il.us/court/Opinions/AppellateCourt/2002/2ndDistrict/March/Html/2001076.htm,
the Court considered a situation in which two parties to a contract each
reasonably relied upon a different portion of that contract to support their
positions. The task before the Court was to decide which provision would give
effect to the intent of the parties.
Defendant was the seller in a real estate transaction for
which the plaintiff was the closing agent. The transaction closed on August 8,
1997, at which time the 1995 real estate taxes on the subject property remained
unpaid, as well as the first tax installment of 1996. Because the buyer would
not accept these exceptions to title, the closing agent and the seller entered
into an indemnity agreement under which the seller was required to place $3,500
in escrow with the closing agent, which sum the closing agent would use to pay
the overdue taxes. According to the agreement, the closing agent was required
to remove the exceptions by August 21, 1997, and upon their removal was to
disburse the remaining funds to the seller.
The closing agent redeemed the 1995 taxes, reimbursed
itself from escrow, and then returned the balance of the escrow funds to the
seller. The closing agent then paid the outstanding 1996 tax payment, and
requested reimbursement from the seller. The seller, however, refused to pay.
The closing agent filed a small claims action, both parties
moved for summary judgment, and the seller made an additional motion for
sanctions. The closing agent’s motion was granted while the seller’s motions
were denied. The seller appealed.
Each party relied on a different clause in the indemnity
agreement to support its position. The seller pointed to a provision that
stated that if the agreement was not terminated within 30 days of a particular
date, the closing agent would charge an annual service fee to be paid out of the
deposit. According to the seller, this provision proved that the primary intent
of the parties was to create a relationship that would terminate within 30 days,
and that the disbursal of the deposited funds terminated the agreement. The
closing agent, however, identified a portion of the agreement that stated that
the seller would forever hold the closing agent harmless from any loss, costs,
damages, etc., which arose on account of the exceptions.
In order to resolve the apparent conflict between these two
provisions, the Court viewed the agreement as a whole in order to determine the
true intent of the parties. The Court concluded that the parties intended for
the seller to be held liable for the expenses the closing agent incurred in
removing the exceptions from the contract. In reaching this conclusion, the
Court explained that the seller’s interpretation violated three well-established
principles of contract construction, while the closing agent’s interpretation
did not.
The Court first addressed the proposition that when two
portions of a contract conflict, it must be determined which portion most
clearly expresses the main purpose of the contract. In this case it was clear
that the main purpose of the agreement was to hold the seller responsible for
the unpaid real estate taxes. The section upon which the closing agent relied
gives effect to this purpose by requiring the seller to indemnify the closing
agent from all expenses incurred on account of the unpaid taxes, and thus
relates to the main purpose of the agreement. The section to which the seller
referred, which relates to fees that may be imposed should the agreement last
longer than 30 days, concerns only a collateral matter.
Next, the Court noted that the clause that the seller
cited, if given effect over the one upon which the closing agent relied, would
render meaningless the term “forever” in the latter clause. If the Court were
to do so, it would violate another principle of contract construction that
requires a contract be construed such that none of its terms are regarded as
mere surplusage. However, this principle of contract construction is not
violated if the word “forever” is given its plain meaning and the clause upon
which the seller relied is found only to mean that fees may be imposed in
certain situations. This reasoning struck another blow against the seller’s
interpretation of the contract.
Finally, the Court recited the principle that specific
provisions in a contract are given more weight than general provisions in the
event of a conflict. The section upon which the closing agent relied was more
specific as it directly addressed the seller’s indemnity obligation, while the
section to which the seller pointed was unrelated to this obligation, and only
peripherally addressed termination of the agreement. Thus, the section upon
which the closing agent relied was given more credence.
The seller argued that the agreement merged into the real
estate deed at closing. In response, the Court noted that two exceptions to the
merger doctrine applied in this case. First, agreements for the execution of
obligations outside the conveyance itself do not merge with a deed at closing.
In this case, the seller’s obligation to indemnify the closing agent was
distinct from the obligation to convey the real property to the buyer. In
addition, duties that are not required to be performed until after the deed is
delivered do not merge. The indemnity agreement required that the exceptions be
removed no later than August 21, 1997, two weeks after closing. Hence, the
agreement did not merge.
For more information, contact Amy McShane, toll free at
888-688-8500, or via e-mail at amcshane@hklaw.com