Strict Performance and Completion Requirements Upheld In Settlement Agreement
January 15, 2003
Martin J. Jaron- Northern Virginia
Against claims of unconscionability and public policy, the
United States Court of Appeals for the Fourth Circuit recently upheld the
default provisions of a settlement agreement requiring strict adherence to the
agreement’s performance and completion requirements. In Jeffrey M. Brown
Associates, Inc. v. Rockville Center, Inc., 7 Fed. Appx. 197, 2001 WL 320896
(4th Cir. 2001), the Fourth Circuit ruled that certain specific contractual
performance and completion requirements that were express conditions precedent
to the contractor’s right to payment were valid and enforceable even where
enforcement meant that the contractor would not be paid, even for that part of
the work actually performed.
The underlying lawsuit arose from a
guaranteed-maximum-price, fast-track, construction contract in which the general
contractor had agreed to design and construct a two-story, retail pavilion,
including a large, underground cinema structure, and a number of required,
public improvements. As work on the project progressed, the property owner
discovered serious defects and deficiencies in the design and construction work.
Ultimately, the property owner filed for arbitration under the construction
contract.
In an effort to salvage the project, remedy the defective
and incomplete design and construction work, and resolve the arbitration, the
parties entered into a settlement agreement pursuant to which the contractor
received a chance to remedy its work and complete the project for which it would
be paid an additional, agreed and final sum subject to the express condition
that the work be fully completed within a specific time. The agreed, final
payment amount was placed in escrow. The settlement agreement spelled out
specific performance and completion requirements and provided that a failure to
achieve completion as specified would constitute a default subjecting the
contractor to immediate termination with no opportunity to cure or right to
further payment.
When the contractor subsequently failed fully to satisfy
the completion requirements within the specified time, the property owner
declared a default and terminated the contractor without further payment. The
escrowed final payment amount was then returned to the property owner.
The contractor, thereafter, brought suit against the
property owner alleging, among other things, breach of contract, and seeking a
declaratory judgment that the settlement agreement provision allowing for
default without payment for work actually done amounted to an unconscionable
forfeiture and penalty in violation of public policy. In its complaint to the
United States District Court for the District of Maryland, the contractor
conceded its failure to fully satisfy the completion requirements. Relying, in
part, on the contractor’s concession, the property owner moved to dismiss. The
District Court, finding that the contractor’s concession “fatally contaminated”
its breach of contract claim, granted the motion, and the contractor appealed.
On appeal, the Fourth Circuit upheld the trial court’s
ruling that the contractor’s admitted failure to meet the express completion
requirements of the settlement agreement relieved the property owner of its
further payment obligations. The Court rejected the contractor’s forfeiture and
penalty arguments finding that, because the contractor had failed to satisfy the
conditions precedent to further payment and was, therefore, not entitled to
receive such payment, the property owner’s refusal to make that payment could
not be a forfeiture. The Court also rejected the contractor’s public policy
arguments finding that the contractor had failed to show how the challenged
contract provisions offended the public good and failed to identify any
constitutional or statutory provision from which the alleged public policy might
be deduced.
The Fourth Circuit’s ruling demonstrates that strict
performance requirements, at least in a settlement agreement (the court
expressed no opinion as to whether the same result would obtain in an action
upon an ordinary construction contract) can be enforced even where enforcement
means that the contractor may not get paid for work performed. As such, the
ruling presents a contrast to the established law allowing quantum meruit
payment to a contractor who has failed to fully complete the work but has,
nevertheless, achieved substantial performance. Interestingly, the contractor
did not raise the concept of substantial performance of the completion
requirements until oral argument; nor was the issue addressed in the Fourth
Circuit’s opinion. Nevertheless, contractors would be well advised to carefully
consider the terms of their agreements whereby payment is made expressly
conditioned upon some specific completion requirements.
For more information, contact Martin Jaron or Dennis
Southard, toll free, at1-888-688-8500.