Corps Issues Revised State General Wetlands Permit for Maryland: Significant Changes Will Impact Many Activities
October 8, 2001
Lawrence R. "Larry" Liebesman- Washington
The Baltimore Corps Office recently issued a revised Maryland State
Programmatic General Permit for activities impacting wetlands and waters, which
became effective in Maryland on October 1, 2001. (MDSPGP-2). This revised
General Permit replaces the General Permit issued in May 1996, and includes
several significant changes that will impact many activities in both tidal and
nontidal wetlands and waters in the state. The General Permit is designed to
delegate many routine activities with minimal impacts
to the Maryland Department of the Environment (MDE) for expedited “one stop
shopping review.” The Corps would retain authority to review activities with
greater impacts under the very detailed federal Clean Water Act Section 404
individual permit (IP) process. The key changes are :
• Impact Limits. The upper threshold of
impacts to waters of the United States, including
jurisdictional wetlands, is reduced from three acres of tidal waters and five
acres of nontidal waters to one acre of tidal or nontidal waters including
adjacent wetlands. This is the
most significant change. Permittees must now determine if direct and indirect
impacts to waters and wetlands for all proposed activities for a “single and
complete” project (including road crossings, utility lines, lot fills and
storm water management facilities) exceed the one-acre threshold. This could
force many projects into the more complex, time consuming and expensive Corps
individual permit process.
• Utility Lines. The new general permit states
a preference for the use of directional drilling, jack and bore, missile or similar methods when feasible in installing utility lines. In the past, permittees have been able to use traditional trenching methods and
best management practices. Now, there is a preference in favor of using these
potentially expensive and difficult alternative methods unless the Corps can be
convinced that such methods are “not feasible.” The Corps, however, does not
define “feasibility” so the applicant is unsure of the amount of evidence
needed to convince the Corps.
• Grandfathering. Only projects that have
either been completed or are uncompleted but have been authorizedunder the first General permit are grandfathered as follows:
• Permittees with uncompleted but grandfathered
projects that also would meet the conditions of the new general permit (e.g.
less than one acre of impact) will have up to three years from the date of the
original authorization to complete the authorized work in waters and wetlands
• Permittees with uncompleted projects that do
not meet the conditions of the new general permit (e.g.. greater than one acre
of impact) will have 12 months from the effective date of the new general permit
(until October 1, 2002) to complete the authorized work in waters and wetlands
• Companies with applications pending are not
grandfathered. This means that a pending application with impacts exceeding one
acre will not qualify for this new General Permit, even though the project may
have been in the planning stage and under Corps review for some time. These
applicants further may have revise their projects in order to qualify for the
new general permit or face the more detailed Corps IP process.
• Compliance Certification. Every permittee must
now submit a signed certification regarding the completed work and required
mitigation.
There are other provisions of the new general permit including a definitional
section and limitations on combining certain activities at a project site that
may affect various projects. Please feel free to contact Lawrence R. Liebesman
at 202-419-2477 or lliebesmn@hklaw.com with any questions on the new Corps
General Permit