Federal Circuit Round Up
March 1, 2000
David Scott "Dave" Black- Northern Virginia
A recent decision by the United States Court of Appeals for the Federal
Circuit, Promac, Inc. v. Togo D. West, Jr., Secretary of Veterans Affairs, No.
99-1075 (Feb. 8, 2000), demonstrates how a contractor with "unclean
hands" can be denied relief for government misconduct.
In this case, a contractor unsuccessfully sought reformation of a contract on
which it was enticed to underbid by a contracting officer's improper conduct. In
1995, the Department of Veterans Affairs issued an invitation for bids (IFB) for
the construction of a research building in Providence, Rhode Island. At the time
the IFB was issued, the VA was only authorized to spend about $2.65 million on
the project.
In the first round of bidding, Promac offered to complete the project for
$3.1 million - which was both the low bid and reasonable, based on the VA's
estimates. However, because the VA had received no additional spending
authority, it was unable to move forward with the procurement as currently
planned. Although, in such circumstances Federal Acquisition Regulation, (FAR)
14.404-1 requires the cancellation of the IFB and the start of a new
acquisition, the contracting officer proceeded to negotiate with the existing
bidders on the false ground that their initial bid prices were
"unreasonable." In addition, during a telephone call, the CO informed
Promac that it should offer a price of around $2.7 million to remain competitive
in the procurement - a communication prohibited by the FAR.
Promac submitted a bid of $2.72 million and was awarded the contract. After
it completed performance of the contract, Promac filed a claim seeking its
original bid price based on the CO's improper conduct in the procurement
process. The Department of Veterans Affairs Board of Contract Appeals granted
the government's motion for summary judgment. Promac appealed, and the Federal
Circuit affirmed.
The Federal Circuit held that the doctrine of unclean hands prevented Promac
from seeking reformation of the contract. According to the court, Promac's hands
were "unclean" because it actively participated in and benefited from
the contracting officer's violations of the procurement regulations. The CO's
decision to negotiate the procurement rather than to start anew benefited Promac
because the new round of bidding would have been open, rather than limited to
the original bidders. In addition, Promac benefited from the CO's disclosure of
a target price by adjusting its bid accordingly while other bidders remained in
the dark. The court noted that, despite the opportunity to do so, Promac had not
complained of the contracting officer's improper conduct at the time the
contract was being procured. It therefore could not seek additional compensation
after completion of the project.