RTOs/ISOs Answer FERC's Large-Load Orders
Market-by-Market Implications for Data Centers and Other Large Loads
Highlights
- After the Federal Energy Regulatory Commission's (FERC) June 2026 large-load show cause orders moved from policy signal to tariff design, six regional grid operators have filed proposed rules that will determine how data centers, advanced manufacturing facilities and other large loads obtain transmission service, post credit support, absorb network-upgrade costs and manage curtailment risk.
- The filings point in the same direction but do not create a national large-load tariff and differ by region, especially on cost, curtailment and whether a project must bring its own power supply.
- These rules will drive how fast a project can be energized, how much cash and credit projects must post, how much upgrades may cost if plans change and how often it may be curtailed.
- Developers, utilities, generators pairing with large loads, investors and lenders should evaluate projects market by market now while comment periods are open and before deadlines pass.
The Federal Energy Regulatory Commission (FERC or the Commission) issued six parallel "show cause" orders on June 18, 2026, under Section 206 of the Federal Power Act (FPA), one for each of the regional grid operators: PJM Interconnection LLC (PJM), Southwest Power Pool Inc. (SPP), New York Independent System Operator Inc. (NYISO), Midcontinent Independent System Operator Inc. (MISO), California Independent System Operator Corporation (CAISO) and ISO New England Inc. (ISO-NE). Each order required the grid operator either to explain why its existing rules were adequate to accommodate large loads or propose changes. FERC's concern was that existing rules for large loads were not built for the speed, size and concentration of new demand from data centers, advanced manufacturing and similar facilities.1
In the show cause orders to the regional transmission organizations/independent system operators (RTOs/ISOs), FERC focused on five core issues:
- clearer application and study processes for large users seeking grid service
- protections so that other customers do not end up paying for upgrades required for a large user
- rules for loads co-located with generation (co-location) or served by generation behind-the-meter (behind-the-meter)
- flexible service options for loads that can reduce usage on request
- creating a coordinated study of generators that serve nearby or co-located loads
FERC stressed that the reforms be forward-looking and continue to leave retail service, siting and rate determinations for the states to determine.
FERC also used a deliberately regional vehicle. The Commission encouraged FPA Section 205 filings so that the markets could propose regionally tailored rules rather than wait for FERC to promulgate a one-size-fits-all rulemaking. That choice matters because the filed frameworks now reflect each region's market design, planning model, resource adequacy construct and note the federal-state allocation of authority.
For background on FERC's June show cause orders, see Holland & Knight's previous alert.
Cross-Cutting Themes
- Common Tools, Different Market Designs. The filings use similar tools (size thresholds, upfront deposits and readiness requirements, public cost reporting, cost recovery contracts and flexible service) but do not suggest a single national approach is emerging. PJM combines generator and large-load studies in one faster process and adds new service types; SPP builds on its existing large-load study and interim service framework, caps regional funding of large-load upgrades and adds a price-responsive non-firm service; NYISO creates new procedures with firm, non-firm and zero-withdrawal service tiers; MISO spreads its reforms across several related filings; CAISO keeps local utilities in the lead and adds an interim flexible connection option; and ISO-NE requires firm-service customers to bring new power supply.2
- Cost-Shift Protection is Becoming the Dominant Organizing Principle. FERC's concern that other customers could be left paying for upgrades built for data centers is now being addressed in contracts. MISO proposes standard cost recovery agreements, financial security tied to required upgrades and a public dashboard. ISO-NE and its transmission owners propose a cost recovery agreement with an exit fee, credit support and direct assignment of upgrade costs to the large user. NYISO builds cost allocation, security agreements and public posting of upgrade summaries into its new procedures. SPP instead caps the regionally funded share of delivery-point upgrades and directly assigns the excess, backed by financial security. PJM's transmission owners are expected to address cost recovery in separate, coordinated filings. For project sponsors, this means more cash and credit committed earlier and continuing exposure if a project is delayed, downsized or abandoned.
- Federal-State Dividing Line is Central to the Filings. Under the FPA, FERC approves jurisdictional transmission rates and tariff terms, while states and local regulators continue to decide retail siting, retail service and retail cost allocation. The new transparency and cost recovery tools do not themselves decide how retail customers ultimately bear FERC-approved transmission costs; however, they may give state commissions better inputs for retail ratemaking.
Region-by-Region Analysis
Each regional discussion below examines the processes the filing would create or revise, the service options it would make available to flexible or staged large loads, the allocation of costs and operational risks and, where relevant, comment deadlines, proposed tariff effective dates, implementation schedules and transition requirements for projects already in development.
PJM: Fast Energization, New Service Products and Operational Controls
PJM's filing is the most sweeping because it responds to the large-load show cause order and PJM's separate co-location proceedings. PJM would require existing large loads to be recorded in a Large Load Registry to establish a baseline, require any increase above that baseline to be studied and create a new "Fast Energization Process" that studies generator and large-load requests together in a single 12-month cycle. PJM also would revise the terms of its Network Integration Transmission Service (NITS).
PJM proposes adding three new service options (Interim Network Integration Transmission Service (NITS), Firm Contract Demand and Non-Firm Contract Demand), which allow a load to connect sooner if it curtails usage under certain conditions. Customers taking these services must show they can reduce usage within five minutes when directed; a first failure to follow a curtailment would trigger a 120-day suspension and a second would end the service.
PJM's treatment of on-site generation is equally significant. It would cap at 50 megawatts (MW) the amount of on-site (behind-the-meter) generation a retail customer can net against its grid usage, with transition, legacy-contract and cogeneration exemptions. PJM requests a 60-day comment period and a March 16, 2027, effective date for several of its proposed changes, with other provisions taking effect later.
SPP: HILL and CHILLS Foundation, Load Safe Harbor Limit and Price Adaptive Load Service
SPP is answering FERC through three Section 205 filings built on tools the show cause order already commended: the High Impact Large Load (HILL) study process and the Conditional High Impact Large Load Service (CHILLS), a non-firm bridge service of up to seven years. For co-located load, SPP proposes no new rates, arguing that its registration and no-netting rules already require such load to pay ancillary service charges on the same basis as all other loads. SPP also asks FERC to hold the show cause proceeding in abeyance and then terminate it without imposing replacement provisions.
SPP's answer to the cost-shift concern is a Load Safe Harbor Limit rather than a pro forma cost recovery agreement. Regionally funded upgrades for each new or modified delivery point would be capped at the lesser of $500,000 per MW of requested load or $25 million, with the excess directly assigned to the requesting customer for up to 40 years and backed by financial security that declines as the assets depreciate. A companion filing would require every HILL study to evaluate grid-enhancing technologies, make SPP's transmission expansion plan searchable and clarify when co-located and behind-the-meter generation must be studied.
For flexible loads, SPP pairs CHILLS with a new Price Adaptive Load Service (PALS), a non-firm service of one to 10 years available only where no new network upgrades are needed. PALS loads are dispatched to zero when local prices exceed $25 per megawatt-hour (MWh), well below the price triggers proposed in MISO, NYISO and ISO-NE, and SPP declined to propose a firm contract demand service because it has no centralized capacity market.
NYISO: LLIP, Withdrawal Service Tiers and State Coordination
NYISO proposes to replace its existing large-load pathway with a new Large Load Integration Procedures framework. Its Large Load definition covers commercial or industrial load of 50 MW or greater located at a single site or in close proximity, with close proximity as being within two miles and two electrical buses and within the same Capacity Region. Unlike FERC's suggested definition, NYISO does not exclude co-located load from the Large Load definition.
NYISO proposes three service tiers:
- Firm Withdrawal Service is for loads that do not strain the region's power supply or transmission system, or that fix any strain they cause.
- Non-Firm Withdrawal Service is for loads that do strain the system but can be dispatched, and they would be curtailed automatically through a mandatory $200/MWh bid cap.
- Zero Withdrawal Service covers loads that do not draw from the grid.
The proposal is also the most explicit about state coordination. NYISO notes that it is a single-state ISO whose boundaries coincide with New York State Public Service Commission retail and resource adequacy jurisdiction, and it proposes a State Exempt Large Load Project concept under which projects identified by the New York State Department of Public Service (NYDPS) would be excluded from the standard application of the Resource Adequacy Impact Standard while remaining subject to transmission-security review.
MISO: LLPR, Cost Recovery and GRITS Options
MISO describes its filing as the latest step in a staged response that already included related filings on generator and load interconnection. The new filing creates a Large Load Project Review (LLPR) process for transmission service requests serving large loads, requires a $250,000 nonrefundable application fee and uses study deposits, milestones and sworn attestations to weed out speculative or duplicate requests.
MISO's cost framework is among the most demanding. The review process would identify the upgrades a project requires, and two standard cost recovery agreements would require the large-load customer to make minimum payments and post financial security for those upgrades. The customer remains responsible for those costs even if the load is never built. MISO also commits to a public, searchable dashboard showing proposed load additions, planned upgrades and estimated costs.
MISO's service options are split across related filings. The joint MISO and transmission owner filing offers Interim NITS (temporary non-firm service while upgrades are built) and Firm Service Step Up (converting to firm service as capacity becomes available). A companion filing would offer firm and non-firm "grid-responsive" service (GRITS) for loads that can operate flexibly rather than waiting for all upgrades. MISO's public fact sheet states that non-firm GRITS customers would have to reduce usage during specified reliability conditions or when local power prices exceed $100/MWh.
CAISO: Flexible Interconnection Within the Existing Market Design
CAISO most strongly argues that reforms should fit its existing market. It notes that CAISO does not offer traditional long-term transmission reservations and does not run a centralized capacity market. It therefore keeps the local transmission-owning utilities, Participating Transmission Owners (PTOs), in the lead on connecting new loads, while adding CAISO rules on visibility, reliability coordination, technical requirements and transparency. CAISO also asks FERC to close its show cause proceeding.
CAISO's central new tool is the Flexible Interim Load Interconnection, which would allow a large load to energize before all grid upgrades are finished, if the utility, CAISO and the customer agree on enforceable operating limits, curtailment conditions, response times, verification and the upgrades needed to end the interim arrangement. CAISO plans to explore a permanent flexible option in 2027.
CAISO also rejects a customer-specific "bring your own generation" requirement. It states that California's resource adequacy obligations remain with load-serving entities and local regulatory authorities, and that the California Public Utilities Commission and other local regulators, not a new CAISO capacity construct, will continue to evaluate whether large loads affect qualifying capacity and procurement needs. That choice makes CAISO materially different from ISO-NE and NYISO.
ISO-NE: Firm Service Tied to New Capacity and Price-Based Redispatch
ISO-NE, New England Power Pool and the PTO Administrative Committee filed a joint proposal. The proposal creates a Large Load construct and three service options: Firm Contract Demand Service, Interim Contract Demand Service and Non-Firm Contract Demand Service. Applications are expected to begin June 1, 2027, with services beginning June 1, 2028.
ISO-NE's most distinctive feature is that firm service would be conditioned on the customer bringing its own new power supply (bring your own new capacity). Interim and non-firm customers would not be counted in the region's capacity planning and would be curtailed before capacity shortages. ISO-NE would curtail non-firm loads when power prices reach $250/MWh and commits to revisiting that level through its stakeholder process.
The ISO-NE package also includes large-load study and generator-interconnection changes, including new procedures for Large Load Co-Located Generators and Large Load Electrically Proximate Generators. Those associated generators may use an expedited interconnection pathway for zero-MW Network Resource Interconnection Service but would not count toward the region's capacity market unless they pursue the ordinary interconnection rights needed for capacity qualification.
What This Means for Market Participants
Connecting a large load involves transmission service, generator interconnection, power supply adequacy, cost recovery, metering and controls, curtailment, siting and retail rates. The same 50 MW project can face very different application windows, deposits, power supply obligations, curtailment exposure and security requirements depending on where it is located.
For developers and end users, the first question is which service level fits the project's business model: full firm service, staged firm service, non-firm or curtailable service, co-located or zero-withdrawal service or interim service while upgrades are built. The second is whether the project can actually deliver the required operating commitments, because several filings treat flexibility as real only if it is backed by telemetry, control systems, demonstrated curtailment response and enforceable agreements. These choices will affect project financing, offtake and site selection.
For utilities, state commissions and incumbent customers, the dominant issue is cost causation. The filings are designed to identify which upgrades are driven by which large loads and reduce the risk that abandoned or delayed projects may leave network-upgrade costs in transmission rates. That transparency will be central to state proceedings over data center tariffs, large-load contracts and cost-sharing arrangements.
Near-Term Action Items
Comment periods are short, and several filings would impose obligations before service is available, including registration, applications, site-control showings, readiness and study deposits, cost recovery agreement negotiations and operational design decisions. Parties that want to influence the final rules should consider participating and filing comments now.
Project sponsors should map their project against each market's transition rules and upcoming application windows, with special attention to projects already undergoing studies or negotiating interconnection and service arrangements. Load-serving entities and utilities should also evaluate whether commercial agreements with large-load customers allocate upgrade costs, financial security, exit risk, curtailment risk and operational compliance obligations in a manner that is consistent with the emerging federal tariff structures.
Finally, parties should monitor companion filings and follow-on stakeholder processes. PJM's transmission owners, FERC's action on SPP's Section 205 filings, New York Transmission Owners and non-incumbent transmission owners, MISO's GRITS filing, CAISO PTOs and ISO-NE PTOs all may materially affect the final allocation of cost, risk and operational responsibility.
Projects that may warrant counsel now include those that:
- are 50 MW or larger, or could grow past that level
- are already in a utility study or negotiating interconnection or service agreements
- plan to co-locate with or rely on on-site or nearby generation
- are counting on interim or flexible service to energize early
- are financing, acquiring or contracting for power from a large-load project whose cost and curtailment risk may change under these rules
Conclusion
FERC did not create one national large-load tariff. The filings in response to FERC's show cause orders confirm that FERC instead has pushed the organized markets toward region-specific frameworks that use common principles of transparency, cost causation, reliability, flexibility and federal-state coordination to produce different market outcomes. That approach is less tidy than a single national rule, but it is likely to be more durable because it tracks the regional, legal and operational differences among PJM, SPP, NYISO, MISO, CAISO and ISO-NE.
Speed to power, co-location, on-site generation, non-firm service and customer-funded upgrades do not mean the same thing in every market, and the path to energization will increasingly turn on tariff rules, region-specific evidence and engagement in these proceedings.
The successful development of large-load projects will increasingly depend on an integrated approach to regulatory, commercial and technical planning. Developers should be prepared to demonstrate that proposed arrangements maintain system reliability, appropriately allocate costs, satisfy applicable tariff requirements and provide adequate certainty to transmission providers, customers and regulators.
For more information or questions, including more granular analysis of a particular RTO or ISO filing, please contact the authors.
Notes
1 See PJM Interconnection LLC, Docket No. EL26-67-000, 195 FERC para. 61,211 (2026); Southwest Power Pool Inc., Docket No. EL26-68-000, 195 FERC para. 61,213 (2026); New York Independent System Operator Inc., Docket No. EL26-69-000, 195 FERC para. 61,216 (2026); Midcontinent Independent System Operator Inc., Docket No. EL26-70-000, 195 FERC para. 61,212 (2026); California Independent System Operator Corp., Docket No. EL26-71-000, 195 FERC para. 61,214 (2026); ISO New England Inc., Docket No. EL26-72-000, 195 FERC para. 61,215 (2026).
2 See PJM, Proposed Tariff Filing, Docket No. ER27-531-000 (filed Nov. 16, 2026); SPP, Proposed Tariff Filing, Docket Nos. ER27-559-000 (filed Nov. 18, 2026), ER27-577-000 (filed Nov. 19, 2026), and ER27-578-000 (filed Nov. 19, 2026); NYISO, Proposed Tariff Filing, Docket No. ER27-517-000 (filed Nov. 16, 2026); MISO, Proposed Tariff Filing, Docket No. ER27-526-000 (filed Nov. 16, 2026); CAISO, Proposed Tariff Filing, Docket No. ER27-532-000 (filed Nov. 16, 2026); ISO-NE, Proposed Tariff Filing, Docket No. ER27-484-000 (filed Nov. 13, 2026).
Information contained in this alert is for the general education and knowledge of our readers. It is not designed to be, and should not be used as, the sole source of information when analyzing and resolving a legal problem, and it should not be substituted for legal advice, which relies on a specific factual analysis. Moreover, the laws of each jurisdiction are different and are constantly changing. This information is not intended to create, and receipt of it does not constitute, an attorney-client relationship. If you have specific questions regarding a particular fact situation, we urge you to consult the authors of this publication, your Holland & Knight representative or other competent legal counsel.